Michigan OSHA citations issued the week of Jun 8, 2026
Week of Jun 8, 2026 · data as of October 5, 2026
89 inspections in Michigan had citations issued between Jun 8, 2026 and Jun 14, 2026, with 314 alleged violation items and $226,320 in proposed penalties. Statuses and current penalties reflect the data as of October 5, 2026.
89inspections with citations issued
314alleged violation items
$226,320initial penalties
$156,820current penalties
About these records. Citations list alleged violations and proposed penalties. Employers can contest them, and many are reduced or withdrawn in settlement. Each row shows the original and the current penalty and a status label derived from the public data as of October 5, 2026. Check the linked osha.gov page for the official record.
| Establishment | Location | Issued | Standards cited | Alleged items | Initial penalty | Current penalty | Status and deadlines | Source |
|---|---|---|---|---|---|---|---|---|
| Williams International Co. LLC | Pontiac | Jun 12, 2026 | 11 | $14,000 | $7,000 | Informal settlementAbatement due Jul 16, 2026 | osha.gov | |
| Fisher & Company dba Fisher Dynamics | Harper Woods | Jun 12, 2026 | 5 | $11,500 | $5,750 | Informal settlementAbatement due Jul 16, 2026 | osha.gov | |
| Gull Lake Marine South Haven | South Haven | Jun 12, 2026 | 10 | $8,000 | $4,000 | Informal settlementAbatement due Jul 16, 2026 | osha.gov | |
| Superior Extrusion Inc. | Gwinn | Jun 12, 2026 | 8 | $7,500 | $3,750 | Informal settlementAbatement due Jul 16, 2026 | osha.gov | |
| Rock Foundations, LLC | Grand Blanc | Jun 12, 2026 | 7 | $5,000 | $5,000 | Final orderAbatement due Jul 1, 2026 | osha.gov | |
| Jermor Plumbing & Heating, Inc. | Southfield | Jun 12, 2026 | 2 | $4,200 | $2,100 | Informal settlementAbatement due Jul 1, 2026 | osha.gov | |
| Middleby Marshall Holding LLC dba NU-VU Food Service Systems | Menominee | Jun 12, 2026 | 1 | $3,500 | $1,750 | Informal settlementAbatement due Jul 16, 2026 | osha.gov | |
| Baumann Building, Inc. | Holland | Jun 12, 2026 | 2 | $2,400 | $1,200 | Informal settlement | osha.gov | |
| G. Fisher Construction Company | Southfield | Jun 12, 2026 | 1 | $2,400 | $1,200 | Informal settlement | osha.gov | |
| Lester Brothers Excavation Inc. | Jackson | Jun 12, 2026 | 1 | $1,500 | $1,500 | ContestedContested Jul 27, 2026 | osha.gov | |
| B & B Rough Carpentry, LLC | Bruce Township | Jun 12, 2026 | 7 | $1,200 | $600 | Informal settlementAbatement due Jul 1, 2026 | osha.gov | |
| All Seasons Heating and Cooling of Mid-Michigan LLC dba All Seasons Heating and Cooling | Midland | Jun 12, 2026 | 4 | $1,100 | $550 | Informal settlementAbatement due Jul 16, 2026 | osha.gov | |
| MJG Michigan LLC dba Burger King #18233 | Ionia | Jun 12, 2026 | 1 | $900 | $900 | Informal settlementAbatement due Jul 16, 2026 | osha.gov | |
| T & J Construction LLC | Utica | Jun 12, 2026 | 7 | $800 | $800 | Final orderAbatement due Jul 1, 2026 | osha.gov | |
| Perfectly Square Exteriors LLC | Grand Rapids | Jun 12, 2026 | 5 | $600 | $600 | Final orderAbatement due Mar 27, 2026 | osha.gov | |
| Provide America LC | Jackson | Jun 12, 2026 | 3 | $600 | $600 | Final orderAbatement due Mar 18, 2026 | osha.gov | |
| Narayan Jyot LLC | Jackson | Jun 12, 2026 | 3 | $600 | $600 | Final orderAbatement due Mar 18, 2026 | osha.gov | |
| Consolidated Electrical Contractors, Inc. | Manistee | Jun 12, 2026 | 1 | $500 | $250 | Informal settlementAbatement due Jul 1, 2026 | osha.gov | |
| New Tech Electric LLC | Utica | Jun 12, 2026 | 5 | $400 | $400 | Final orderAbatement due Jul 1, 2026 | osha.gov | |
| Kincaid Henry Building Group, Inc. | Manistee | Jun 12, 2026 | 3 | $400 | $400 | Final order | osha.gov | |
| Geocycle LLC dba CM Rubber Recycling | Coleman | Jun 12, 2026 | 2 | $400 | $400 | Final orderAbatement due Jul 16, 2026 | osha.gov | |
| Aab Electric LLC | Nunica | Jun 12, 2026 | 3 | $0 | $0 | Final orderAbatement due Jul 1, 2026 | osha.gov | |
| Brown Bros Excavating, LLC | Flint | Jun 12, 2026 | 5 | $0 | $0 | Final orderAbatement due Jun 18, 2026 | osha.gov | |
| Roberts Masonry, Inc. | Manistee | Jun 12, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Shugart Builders, Inc. | Alden | Jun 11, 2026 | 7 | $4,500 | $2,250 | Informal settlementAbatement due Jun 30, 2026 | osha.gov | |
| Energy Steel & Supply Co. | Rochester Hills | Jun 11, 2026 | 6 | $4,200 | $4,200 | Final order | osha.gov | |
| Milbocker and Sons, Inc. | Kalamazoo | Jun 11, 2026 | 1 | $4,200 | $4,200 | ContestedContested Jun 30, 2026 | osha.gov | |
| Great Lakes Subs LLC dba Jersey Mike's Subs | Flint | Jun 11, 2026 | 1 | $2,500 | $1,250 | Informal settlementAbatement due Jul 15, 2026 | osha.gov | |
| Anglin Civil, LLC | Inkster | Jun 11, 2026 | 2 | $1,000 | $500 | Informal settlementAbatement due Jun 30, 2026 | osha.gov | |
| Semper FI Builders, Inc. | South Haven | Jun 11, 2026 | 6 | $800 | $800 | Final orderAbatement due Jun 30, 2026 | osha.gov | |
| Ervin Amasteel Industries Division of Ervin Industries | Adrian | Jun 11, 2026 | 1 | $700 | $350 | Informal settlement | osha.gov | |
| American Classic Roofing & Building Supply | Oshtemo | Jun 11, 2026 | 3 | $500 | $500 | Final orderAbatement due Jun 30, 2026 | osha.gov | |
| Precision Concrete Cutting & Demolition, LLC | Alden | Jun 11, 2026 | 2 | $400 | $400 | Final order | osha.gov | |
| Triple C Carpentry LLC | Grand Rapids | Jun 11, 2026 | 6 | $400 | $400 | Final orderAbatement due Jun 30, 2026 | osha.gov | |
| Steven Walters Builder, LLC | South Haven | Jun 11, 2026 | 5 | $400 | $400 | Final order | osha.gov | |
| Lake Orion Community Schools - Community Education Resource Center | Lake Orion | Jun 11, 2026 | 1 | $0 | $0 | Final orderAbatement due Jul 29, 2026 | osha.gov | |
| Aaa Underground, LLC | Taylor | Jun 11, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Merritt Electric LLC | Portage | Jun 11, 2026 | 1 | $0 | $0 | Final orderAbatement due Jun 30, 2026 | osha.gov | |
| JBR Construction LLC | Romulus | Jun 11, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Midwest Pavement Contracting, Inc. | Ypsilanti | Jun 11, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| B. A. McLaren and Sons Plumbing LLC | Haslett | Jun 11, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Hunter Construction Services, Inc. | Kalamazoo | Jun 11, 2026 | 1 | $0 | $0 | Final orderAbatement due Jun 30, 2026 | osha.gov | |
| The DM Burr Group - Facilities Management | Lake Orion | Jun 11, 2026 | 1 | $0 | $0 | Final orderAbatement due Jul 29, 2026 | osha.gov | |
| B & B Building & Mechanical LLC | Portage | Jun 11, 2026 | 2 | $0 | $0 | Final orderAbatement due Jun 30, 2026 | osha.gov | |
| Ajax Heating & Air Conditioning | Portage | Jun 11, 2026 | 1 | $0 | $0 | Final orderAbatement due Jun 30, 2026 | osha.gov | |
| Quantum Companies, Inc. | Lansing | Jun 11, 2026 | 2 | $0 | $0 | Final orderAbatement due Jun 30, 2026 | osha.gov | |
| Superior Mechanical, LLC | Lansing | Jun 11, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| A4H Construction LLC | Lansing | Jun 11, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| The Detroit Tubing Mill Inc. | Detroit | Jun 10, 2026 | 12 | $18,120 | $18,120 | Final orderAbatement due Jul 14, 2026 | osha.gov | |
| Trinity Truck and Trailer Service LLC | Ithaca | Jun 10, 2026 | 8 | $8,000 | $4,000 | Informal settlementAbatement due Jul 14, 2026 | osha.gov | |
| Alta Construction Equipment LLC | New Hudson | Jun 10, 2026 | 5 | $6,400 | $6,400 | ContestedAbatement due Jul 14, 2026Contested Jul 22, 2026 | osha.gov | |
| Metal Technologies - Precision Gage | Hillsdale | Jun 10, 2026 | 2 | $5,800 | $1,200 | Informal settlementAbatement due Jul 21, 2026 | osha.gov | |
| Berry Green Processing LLC | Warren | Jun 10, 2026 | 4 | $3,700 | $3,700 | Final order | osha.gov | |
| Crown Industrial Services Inc. | Jackson | Jun 10, 2026 | 5 | $2,900 | $2,900 | Final orderAbatement due Jul 21, 2026 | osha.gov | |
| Cancer & Hematology Centers | Grand Rapids | Jun 10, 2026 | 1 | $2,100 | $2,100 | ContestedAbatement due Jul 21, 2026Contested Aug 13, 2026 | osha.gov | |
| Livingston County Drain Commissioner | Howell | Jun 10, 2026 | 3 | $2,100 | $1,050 | Informal settlementAbatement due Jul 14, 2026 | osha.gov | |
| Matthew and Deborah Miller | Jackson | Jun 10, 2026 | 11 | $1,600 | $1,600 | Final orderAbatement due Jun 29, 2026 | osha.gov | |
| High Performance Metal Finishing | Portage | Jun 10, 2026 | 7 | $1,500 | $750 | Informal settlementAbatement due Jul 14, 2026 | osha.gov | |
| Fox Ann Arbor Acura | Ann Arbor | Jun 10, 2026 | 6 | $800 | $800 | Final orderAbatement due Jul 14, 2026 | osha.gov | |
| Burnash Wrecking, Inc. | Flint | Jun 10, 2026 | 2 | $700 | $700 | Final orderAbatement due Jul 14, 2026 | osha.gov | |
| Triangle Associates, Inc. | Saint Johns | Jun 10, 2026 | 2 | $700 | $700 | ContestedAbatement due Jun 29, 2026Contested Aug 14, 2026 | osha.gov | |
| Reconserve of Michigan Inc. | Battle Creek | Jun 10, 2026 | 1 | $600 | $600 | Final orderAbatement due Aug 25, 2026 | osha.gov | |
| Gale Plumbing and Hydronics, Inc. | Saint Johns | Jun 10, 2026 | 1 | $500 | $0 | Informal settlement | osha.gov | |
| R. C. Hendrick & Son, Inc. | Saint Johns | Jun 10, 2026 | 2 | $500 | $500 | Final orderAbatement due Jun 29, 2026 | osha.gov | |
| J and B Interior LLC dba Auto Interior Decorators Inc. | Saginaw | Jun 10, 2026 | 1 | $400 | $200 | Informal settlementAbatement due Jul 14, 2026 | osha.gov | |
| Custom Electric Inc. | Haslett | Jun 10, 2026 | 1 | $100 | $100 | Final order | osha.gov | |
| Oakland Community College | Auburn Hills | Jun 10, 2026 | 1 | $0 | $0 | Final orderAbatement due Jul 14, 2026 | osha.gov | |
| JC Electric LLC | Saint Johns | Jun 10, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| M/I Homes, Inc. | Chelsea | Jun 10, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| DSC Laboratories LLC | Muskegon | Jun 9, 2026 | 21 | $22,000 | $22,000 | ContestedAbatement due Jul 13, 2026Contested Aug 6, 2026 | osha.gov | |
| Eagle T M C Technologies | Muskegon | Jun 9, 2026 | 5 | $16,800 | $8,400 | Informal settlementAbatement due Jul 13, 2026 | osha.gov | |
| Supreme Machined Products, Inc. | Spring Lake | Jun 9, 2026 | 8 | $12,100 | $6,050 | Informal settlementAbatement due Jul 13, 2026 | osha.gov | |
| River City Metal Products Inc. | Comstock Park | Jun 9, 2026 | 2 | $4,200 | $4,200 | Final orderAbatement due Jul 13, 2026 | osha.gov | |
| Gentex Corporation | Zeeland | Jun 9, 2026 | 2 | $4,000 | $2,000 | Informal settlementAbatement due Jul 13, 2026 | osha.gov | |
| Wyatt Chevrolet GMC | Whitehall | Jun 9, 2026 | 9 | $2,700 | $2,700 | Informal settlementAbatement due Jul 13, 2026 | osha.gov | |
| Northern Precision Products | Leroy | Jun 9, 2026 | 3 | $2,300 | $1,150 | Informal settlementAbatement due Jul 13, 2026 | osha.gov | |
| Huron Transit Corporation dba Thumb Area Transit | Bad Axe | Jun 9, 2026 | 4 | $1,700 | $850 | Informal settlementAbatement due Jul 13, 2026 | osha.gov | |
| Dumbarton Tool, Inc. | Cadillac | Jun 9, 2026 | 9 | $1,600 | $1,600 | ContestedAbatement due Jul 13, 2026Contested Jul 15, 2026 | osha.gov | |
| San Fran LLC | Lincoln Park | Jun 9, 2026 | 5 | $800 | $400 | Informal settlement | osha.gov | |
| City of Manistee Fire Department | Manistee | Jun 9, 2026 | 1 | $400 | $400 | Final orderAbatement due Jul 20, 2026 | osha.gov | |
| Causeway Bay Lansing Hotel & Convention Center | Lansing | Jun 9, 2026 | 1 | $0 | $0 | Final orderAbatement due Jul 20, 2026 | osha.gov | |
| Isaacson Construction Services, LLC | Jackson | Jun 9, 2026 | 1 | $0 | $0 | Final orderAbatement due Jun 26, 2026 | osha.gov | |
| Cal's Excavating Inc. | Jackson | Jun 9, 2026 | 2 | $0 | $0 | Final order | osha.gov | |
| Oliver Concrete Inc. | Saginaw | Jun 9, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| J-Line Trenching LLC | Howell | Jun 9, 2026 | 2 | $0 | $0 | Final order | osha.gov | |
| F and M Concrete Construction LLC | Linden | Jun 9, 2026 | 2 | $0 | $0 | Final orderAbatement due Jun 26, 2026 | osha.gov | |
| Potts Masonry Incorporated | Holland | Jun 8, 2026 | 3 | $12,000 | $6,000 | Informal settlementAbatement due Jul 24, 2026 | osha.gov | |
| Synergy Prototype Stamping LLC | Clinton Township | Jun 8, 2026 | 1 | $1,600 | $800 | Informal settlement | osha.gov | |
| Synergy Additive Manufacturing, LLC | Clinton Township | Jun 8, 2026 | 2 | $500 | $250 | Informal settlementAbatement due Jul 10, 2026 | osha.gov |
Standards cited this week
- 1910.1200 Hazard Communication (11)
- 1926.501 Fall Protection (10)
- 1910.147 Lockout/Tagout (9)
- 1926.100 Hard Hats (6)
- 1910.22 Walking-Working Surfaces (3)
- 1910.134 Respiratory Protection (3)
- 1910.1001 Asbestos (3)
- 1926.102 Eye and Face Protection (3)
- 1926.1101 Asbestos in Construction (3)
- 1910.303 Electrical General (3)
- 1910.146 Confined Spaces (2)
- 1926.503 Fall Protection Training (2)